Microsoft

Microsoft 70-178 – Study Guide Free Download Of Latest Microsoft 70-178 With All New Exam Questions

QUESTION 1
A section of your project contains only a summary task along with four subtasks and a milestone.
You discover that the section is located in the incorrect phase and has the incorrect Work Breakdown Structure (WBS) numbering.
You need to move the section to another phase of the project. You also need to ensure that the section reflects the correct WBS numbering.
What should you do?

A. Select the summary task and change the scheduling mode to Manually Scheduled.
B. Select the entire section and click Move Task.
C. Drag the summary task.
D. Modify the start and finish dates of the summary task. Correct Answer: C
Explanation Explanation/Reference:
QUESTION 2
You have a Project 2010 schedule that contains the following tasks:
Inactive tasks

Manually scheduled tasks
Manually scheduled summary tasks
Tasks that contain strikethrough font
You want to save the schedule as a Project 2007 project.
You need to ensure that no new milestones are created.
What should you do?
A.
Change all inactive tasks to active tasks.
B.
Change all tasks that contain strikethrough font to tasks that include normal font.
C.
Change all manually scheduled summary tasks to automatic scheduling.
D.
Change all manually scheduled tasks to automatic scheduling.

Correct Answer: A Explanation Explanation/Reference:
QUESTION 3
You manage several projects. Each project has shared resources and work distribution.
You need to ensure that you can adjust the workload for specific resources used across multiple project schedules.
What should you do?

A. Enable the Load Summary Resource Assignments option. Then, select the Level Resource function on each project.
B. Open the individual schedules and use the Visual Reports option. Then, use the Resource Usageview to manually modify resource Work.
C. Open a blank project and select Insert Subproject for each project schedule. Then, use the Level Resource function for selected resources.
D. Open the shared Resource Pool for each project schedule. Then, use the Level Resources function.
Correct Answer: C Explanation Explanation/Reference:
QUESTION 4
You manage a project that specifies all constraint types to As Soon As Possible.
You discover that one of your key tasks is scheduled to end prior to the targeted finish date.
You need to display the targeted finish date on the default Gantt chart.
What should you modify in the Task Information window?

A. Set the Deadline date field.
B. Set the Constraint date field.
C. Set the Finish date field.
D. Select the Mark task as milestone check box.
E. Select the Display on Timeline check box. Correct Answer: A
Explanation Explanation/Reference:
QUESTION 5
The first major phase of your project is scheduled for a duration of 45 days. However, you do not have task information for other phases. You need to indicate that the duration of the entire project is 200 days. What should you do?
A. Select the Project Summary Task option.
B. Select the Summary Tasks option.
C. Create a manually scheduled summary task.
D. Update the project calendar.
Correct Answer: C Explanation Explanation/Reference:
QUESTION 6
The project you manage has only part-time resources.
The part-time resources work four hours a day from Wednesday through Saturday.
You need to create a new calendar and set the calendar as the default for your project.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

A. Select the part-time calendar from the Change Working Time window.
B. Set the calendar type to part-time for all tasks.
C. Select the part-time calendar from the Project Information window.
D. On the Project tab, Select Change Working Time, and then click Create New Calendar.
E. Change the Calendar type in the Project Options dialog box. Correct Answer: CD
Explanation Explanation/Reference:
QUESTION 7
You need to set the default constraint type for all new tasks to As Late As Possible. What should you do?
A. Select all tasks, and then click Layout.
B. In the Options dialog box, enable the New Tasks are effort driven check box.
C. Select all tasks, and then set the constraint type to As Late As Possible.
D. In the Project Information window, from the Schedule From drop-down list box, select Project Finish Date. Correct Answer: D
Explanation Explanation/Reference:
QUESTION 8
You manage a project according to the schedule as shown in the exhibit. (Click the Exhibit button.)

You need to set the Task Mode for task 4 to be the same as task 6. What should you do?
A. Create a task dependency from Task 4 to Task 6.
B. Set Task 4 as critical.
C. Add a 1 day lead to Task 4.
D. Set Task 4 as manually scheduled.
Correct Answer: D Explanation Explanation/Reference:
QUESTION 9
You use bottom-up scheduling. You need to group four consecutive tasks in a major phase. You highlight the four tasks. Which command should you use?
A. Outdent
B. Fill Down
C. Insert Summary
D. Move Task Correct Answer: C
Explanation Explanation/Reference:
QUESTION 10
You need to view Task ID 0 on your project plan. What should you do?
A. On the Advanced tab of the Project 2010 options, select Show Status Bar.
B. On the Format tab, select Summary Tasks.
C. On the Format tab, select Project Summary Task.
D. Insert a new Summary Task. Correct Answer: C
Explanation Explanation/Reference:

microdess
We are a team that focuses on tutoring Microsoft series certification exams and is committed to providing efficient and practical learning resources and exam preparation support to candidates. As Microsoft series certifications such as Azure, Microsoft 365, Power Platform, Windows, and Graph become more and more popular, we know the importance of these certifications for personal career development and corporate competitiveness. Therefore, we rely on the Pass4itsure platform to actively collect the latest and most comprehensive examination questions to provide candidates with the latest and most accurate preparation materials. MICROSOFT-TECHNET not only provides the latest exam questions, but also allows candidates to find the required learning materials more conveniently and efficiently through detailed organization and classification. Our materials include a large number of mock test questions and detailed analysis to help candidates deeply understand the test content and master the answering skills, so as to easily cope with the test. In addition, we have also specially launched exam preparation materials in PDF format to facilitate candidates to study and review anytime and anywhere. It not only contains detailed analysis of exam questions, but also provides targeted study suggestions and preparation techniques so that candidates can prepare more efficiently. We know that preparing for exams is not just about memorizing knowledge points, but also requires mastering the correct methods and techniques. Therefore, we also provide a series of simulation questions so that candidates can experience the real examination environment in the simulation examination and better adapt to the examination rhythm and atmosphere. These simulation questions can not only help candidates test their preparation results, but also help candidates discover their own shortcomings and further improve their preparation plans. In short, our team always adheres to the needs of candidates as the guide and provides comprehensive, efficient and practical test preparation support to candidates. We believe that with our help, more and more candidates will be able to successfully pass the Microsoft series certification exams and realize their career dreams.